Small-Scale Embedded Generation (SSEG) Feed-In Tariffs
The Western Cape Government (WCG) is focused on ensuring a supportive regulatory environment for SSEG across municipalities. This will enable solar PV systems to be grid-tied and feed in any excess electricity generated. Many municipalities already have the rules and tariffs in place, and the remaining municipalities are supported by the WCG. Find out what the tariff is in your municipality for your home in the table below listed in alphabetical order. Find out more about installing solar PV.
Please note that links for the table below are only active for those municipalities that have SSEG Tariffs:
Beaufort West | Cederberg | Kannaland | Mossel Bay | Stellenbosch |
Bergrivier | City of Cape Town | Knysna | Oudtshoorn | Swartland |
Bitou | Drakenstein | Laingsburg | Overstrand | Swellendam |
Breede Valley | George | Langeberg | Prince Albert | Theewaterkloof |
Cape Agulhas | Hessequa | Matzikama | Saldanha Bay | Witzenberg |
Residential Tariffs
Category | Monthly Charges | Export Tariff (Flat) | Export Tariff (ToU) | |
---|---|---|---|---|
Beaufort West | Green Energy (Domestic) | SSEG additional cost - R129.37 |
Low Season High Season |
|
Bergrivier | SSEG | No additional monthly charges for SSEG connections | 0.75 c/kWh | |
Bitou | SSEG Single Phase | Basic Charge for SSEG customers - R582.10 | 83.730c/kWh | |
Bitou | SSEG Three Phase | Basic Charge for SSEG customers - R1323.80 | 95.760c/kWh | |
Breede Valley | SSEG (Residential) | An additional meter reading, admin and maintenance fee may also be applicable. | 89.61c/kWh | |
Cape Agulhas | SSEG Feed In Tariff (Residential) |
Fixed network charge for SSEG customers - R471,13/month Bulk customers to retain original KVA capacity and demand charges. |
101.16 c/kWh | |
Cape Town | Residential SSEG | Additional Advanced Metering Infrastructure access charge for SSEG customers - R90.00 |
Feed in tariff - 78.98 c/kWh, Green attributes will pass to the City. Feed in incentive - 25c/kWh, Applicable until 30 June 2025 |
|
Cederberg | Time of Use LV Self Generator | Basic Charge - R2671.2407/month Demand Charge – R122.6734/KVA Access Charge - R91.2268 Charges are applicable to all TOU customers regardless of SSEG status |
Low Season High Season |
|
Drakenstein | Co-Generation | The fixed charge regime depends on the customer's category regardless of SSEG status | 66.39 c/kWh | |
George | Embedded Generation/ Municipal purchase tariff | The additional Basic charge for SSEG customers - R100/month + The standard Bulk TOU reactive energy charge |
Low Season High Season |
|
Hessequa | SSEG Feed In | The fixed charge regime depends on the customer's category regardless of SSEG status | 66.17 c/kWh | |
Knysna | SSEG | Basic charge with buyback - R258.79/month Access charge - R11.83/amp |
74c/kWh | |
Laingsburg | Unit rates | No additional charges for SSEG connections | 201.18 c/kWh | |
Langeberg | SSEG Feed In | No additional charges for SSEG connections | 66.39 c/kWh | |
Mossel Bay | SSEG Single Phase | Fixed Network Charge for SSEG customers – R457.02 /month | 102.00c/kWh | |
Mossel Bay | SSEG Three Phase | Fixed Network Charge Charge for SSEG customers - R30.96/month/3 phase amp | 102.00c/kWh | |
Oudtshoorn | Bulk Time of Use LV (400V) for Pilot Only | No additional charges for SSEG connections |
Low Season High Season |
|
Overstand | SSEG | No additional charges for SSEG connections | 90.17c/kWh | |
Prince Albert | SSEG | Basic charge - R370.77 | 53.74 c/kWh | |
Saldanha Bay | SSEG Feed in Tariff Single Phase | No additional charges for SSEG connections | 73.00 c/kWh | |
Stellenbosch | Renewable Energy (DOM5) Generation of own use and export | Renewable Energy Generation for own use and export Basic Charge - R229.69 Reading Charge R103.95 |
Low Season High Season |
|
Swartland | Net Metering Tariff | Network Charge - R268.81 | 108.7413c/kWh | |
Theewaterskloof | SSEG |
Additional Basic Charge - R80.2130/month/POS Subject to the customer being on theTOU and signing a new supply agreement |