Type | Activity | Start | End | Start Date | End Date |
Day Closure | Asphalt Overlay | Pniel Intersection | Franschhoek | Sept 24 | 12 Dec 24 |
Day Closure | Service ducts, Bypass | Old Paarl Road | Le Bonheur | Oct 24 | 30 Nov 24 |
24hour Closure | Service ducts, Bypass | Vrede & Lust | Pniel Intersection | Sept 24 | 12 Dec 24 |
Sections 2 and 3: The STOP/GO operation will be completed before the December 2024 builders break and two way traffic will be allowed from January 2025 while the permanent works on RHS will be constructed.
*Disclaimer: Dates are estimated and may change due to unforeseen circumstances.